Day 5 of the 6 day shift cycle. Shift 8:00 pm till 4:00 am
Press - Mulder
Tiles made: Ventilation 33 Xahara 4500
Dry Tiles unstacked: Faiteaux Xahara, Demi-Ronde 33 Noir

Man I was tired. Up at 7:00 am to get the kids to school (last day before hols) Shopping with Fi till midday. Lawn mowed and cuttings taken to the tip and then start an 8 hour shift.

The grappins had a bust sensor so the mechanics had to pirate one from the other line. (What they'll do when that line is action, I don't know, probably pirate it back again). There were 3 guys on leave and because we were unstacking the faiteaux, we needed an extra guy to turn them. So the boss had to get out of his office and work on the line. Cool